 Ascot Foreshore Stabilisation Works and Path Closure

The City will be undertaking urgent stabilisation works along the foreshore path adjacent to Ascot Racecourse throughout October.

Works will involve the installation of gabion baskets, reno mattresses, fill and limestone spalls as well as revegetation, along 10 linear metres. This site is immediately adjacent to similar works completed in 2015.

Due to safety reasons, there will be no public access along this section of path for the duration of the project.

Pedestrians and cyclists will be redirected along Grandstand Road and Matheson Road, with redirection signage installed along the route. Works are to commence 9 October with the path due to be reopened on 26 October, 2018.